Vienna’s Tram Line 18 to Be Extended

The new service will begin in September 2026, when the tram will operate the full route from Stadion to the U6 station Burggasse-Stadthalle.
U2 U-Bahn Line Fully Reopens

From December 6, the line will operate its full route, running from Seestadt to Karlsplatz, more than a year later than originally planned.
September Flood Causes Major Delays to U-Bahn Project

Despite protective measures, the U-Bahn construction site at Pilgramgasse filled with 19,000 cubic metres of water, destroying machinery and vehicles.
Vienna U-Bahn Resumes Normal Service

Vienna’s U2, U3, U4 and U6 U-Bahn lines resume normal service on Wednesday following several days of disruption caused by severe weather and flooding over the weekend.
Flooding Stops Some Vienna U-Bahn Services and Forces Evacuations

Service on Vienna’s U-Bahn lines U2, U3, U4 and U6 has been partially suspended due to continuous heavy rain, with some areas in western Vienna hit by floodwaters.
U-Bahn Extension Delayed, Costs Rise

Technical problems and inflation have delayed the construction of the U2 extension to 2030, instead of the initially planned 2028.
Long-Delayed U-Bahn Section to Reopen in September

The segment between Schottentor and Karlsplatz stations will reopen after a prolonged closure, further delayed by construction issues.